Heavy Civil & Mineral Processing InfrastructureCopperbelt Regional Gateway, Zambia

250T Heavy Crane Fleet & Concrete Machinery Mobilization for Plant Expansion

Result: 250T crawler cranes, high-pressure concrete pumps, and heavy tippers deployed with certified master riggers.
01 · Operational Challenge

Supply Bottlenecks & Exposure

Moving abnormal, oversized heavy cranes and concrete boom pumps across intercontinental corridors for a tight 120-day mill expansion turnaround.

02 · Logistics Integration

Direct Sourcing & Bonded Buffer Staging

Zabion executed route clearance surveys, ocean breakbulk shipping, and lowbed multi-axle convoy transit with on-site assembly technicians and certified operators.

03 · Operational Outcome

Production Impact

Completed critical SAG mill headframe and autoclave placement 6 days ahead of scheduled plant turnaround with zero safety incidents.

"Mobilizing a 250T crawler crane into an active mine expansion without road permit delays was critical to meeting our plant commissioning deadline."
Project Construction Director, Mining EPC Infrastructure Contractor
Deployment Parameters
Client Profile
EPC Mine Infrastructure Contractor
Geography
Copperbelt Regional Gateway, Zambia
Cargo Moved
250T Lattice Boom Crawler Crane, 42m Mobile Concrete Boom Pump, 50T Heavy Tipper Trucks
Volume / Tonnage
12 Capital Heavy Machinery Units
Multimodal Routing
OEM Manufacturing Centers (Europe & Asia) → Copperbelt Plant Expansion Site, Zambia
Framework Timeline
45-day mobilization and on-site commissioning